The Requirements of 40 CFR 265.55 Emergency Coordinator for Large Quantity Generator of Hazardous Waste
This article is the seventh in a series that takes a close look at the requirements of 40 CFR 265, Subpart D – Contingency Plan and Emergency Procedures. This Subpart, along with the remainder of Part 265 is applicable to permitted hazardous waste treatment, storage, and disposal facilities (TSDFs) and to large quantity generators of hazardous waste (LQGs). A Contingency Plan and the emergency procedures outlined in Subpart D are critical for the safe operation of a hazardous waste facility and to ensure compliance with state and Federal regulations.
The purpose of this article is to read, review, and explain the requirements of 40 CFR 265.55 Emergency Coordinator.
Hold on a minute! These regulations were revised and moved to a new location within Title 40 of the CFR by the Generator Improvements Rule. If your state has not yet adopted the Generator Improvements Rule, then this article is still applicable to you (but it won’t be for much longer). If your state has adopted and been authorized to enforce the Generator Improvements Rule, then these regulations no longer apply to you. Read: What is the status of the Generator Improvements Rule in my state?
To see an explanation of these regulations as revised by the Generator Improvements Rule you must refer to the following:
Not sure of your hazardous waste generator status? |
Read the previous article in this series: 40 CFR 265.54 Amendment of Contingency Plan or read on to learn about 40 CFR 265.55.
To see an explanation of the regulations prior to the revisions of the Generator Improvements Rule, please continue reading this article.